Italy
In the last quarter of 2018, we created an underwater metal structure, "Cofferdam", consisting of dn 1,000 pipes 33 meters long and AZ48-700 metal sheet piles 28 meters long and installed a metal door, "Gate", positioned in the center of the structure. The final height of the structure varies from -9.00 to -14.00 m above sea level
Means, equipment and operators used
- Means: Adhemar De Saint-Venant ship with DP2 dynamic positioning system
- Equipment used: two LARS systems (Launch And Recovery System), a decompression chamber, a control room and a PTC 120 vibrodriver
- Special equipment: GPS control system for diving divers
- Personnel: a supervisor, 9 technical underwater operators and 2 operators for vibroinfissor
- Number of dives performed: 110
- Maximum working depth: -24.00 m asl
- Injuries: 0
Duration: October 2018 - December 2018.
All diving and vibrodriving equipment is our property and has been transported and installed on board.
Albania
We have created the entire structure that allows the arrival on the ground of a 1,000 mm diameter gas pipeline. The “cofferdam” metal structure with a length of 700.00 m was built half on the ground and half on the sea and is made up of two parallel metal sheet piles and thrust structures built on site and positioned inside them.
To allow the insertion of the metal elements, starting from the shoreline, a temporary cliff made of stone material with a length of 300.00 m positioned along the north side of the cofferdam was created. The construction of the cliff required the supply and installation of 60,000 tons of stone material of various sizes.
To allow the pipeline to arrive, was carried out, within the cofferdam, the dredging of the seabed with a narrow section and constant slope. The dredged volume was 20,000 cubic meters.
Means, equipment and operators used
- Means: 2 crawler cranes, 2 vibrodriver, 3 hydraulic excavators
- Special equipment: drone for performing bathymetric surveys with GPS system
- Personnel: 4 site technicians 13 operators
- Injuries: 0
Duration: from September 2018 - in progress.
All the means and equipment used are our property.