Work is carried out at the NIGERIA LNG (NLNG) plant at Bonny Island - Nigeria.
The realization of the project Nigeria LNG Train 7 has been entrusted, in May 2020, to joint venture made up by Saipem and Daewoo E&C Co.
Nautilus’ role
The works entrusted to Nautilus consist in the installation of a total of 105 metal piles that will constitute the foundation structures of the new dock which will have a total length of 385.00 meters.
The metal piles will have various dimensions with a diameter between 1.219 mm and 1.422 mm, length between 32.00 and 59.70 ml and a weight varying from 21,000 to 38,000 kg.
All the metal elements will be fixed by water using boats and equipment owned by Nautilus (“Ercole” pontoon, “Sepone” jack-up platform, PTC 120 vibratory hammer, Junttan HHX300 hydraulic hammer).